Each product has a specific timeframe for foot traffic and heavy equipment. The drying time is very dependent on the climate and surroundings:

  • Epoxy coatings generally take about 4-5 days to install depending on the size, scope and prep work of the particular project.

  • Stain floors take approximately 5-6 days to complete and 1-2 days of drying time.

  • Floor removal varies greatly depending on conditions.

  • Re-sealing driveways and sidewalks generally takes 2 days to complete and 1-2 days of drying time.

The above are only some general guidelines for our products. If you have a specific question regarding your project, please contact us at 812-325-1633.